[Isocops] IBEX Orbit #468 LGC ATS Approval ( 20 Nov 2019 ) - v001 approval
KEN FAIRCHILD
fair-play at comcast.net
Fri Nov 8 10:42:26 EST 2019
All,
I have looked at the orbit 468 Lo gain test ATS,
IBEX_2019_323_o0468a_LCG_v001.scr,
and I approve.
There are no constraint violations in
IBEX_2019_323_o0468a_LGC_v001.ccvr.
The commands in the v001 ATS match those in the v001 STF,
IBEX_2019_323_o0468a_v001_lgc.stf.
The timing is such that, as planned, the gain test starts a few hours (about 7) after 15 Re ascending.
Ken
> On November 5, 2019 at 4:47 PM "Perry, Timothy E [US] (IS)" <Timothy.Perry at ngc.com> wrote:
>
>
> All,
>
> Attached are the planning files for Orbit #468
>
> Please respond to this thread with comments and approvals.
>
> Approvals are required by COB on 19 Nov 2019
>
> Duration of the calibration is from 019/11:20:08:00:00 to 2019/11:20:12:31:36
>
>
>
> Timothy E.Perry
>
> CRS IBEX OCO-2
>
> Mission Operations
>
> timothy.perry at ngc.com
>
> Office (703) 406-5976
>
> Cell (301) 606-1430
>
>
>
> [cid:image001.png at 01D542D6.6047A400]
>
>
>
>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.sr.unh.edu/pipermail/isocops/attachments/20191108/3a65ed90/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 5047 bytes
Desc: not available
URL: <https://lists.sr.unh.edu/pipermail/isocops/attachments/20191108/3a65ed90/image001.png>
More information about the Isocops
mailing list