All,

I have looked at the orbit 468 Lo gain test ATS,

IBEX_2019_323_o0468a_LCG_v001.scr,
 
and I approve.
 
There are no constraint violations in
 
IBEX_2019_323_o0468a_LGC_v001.ccvr.
 
The commands in the v001 ATS match those in the v001 STF,
 
IBEX_2019_323_o0468a_v001_lgc.stf.

The timing is such that, as planned, the gain test starts a few hours (about 7) after 15 Re ascending.

Ken
   
On November 5, 2019 at 4:47 PM "Perry, Timothy E [US] (IS)" <Timothy.Perry@ngc.com> wrote:

All,

   Attached are the planning files for Orbit #468

Please respond to this thread with comments and approvals.  

Approvals are required by COB on 19 Nov 2019

Duration of the calibration is from  019/11:20:08:00:00 to 2019/11:20:12:31:36

 

Timothy E.Perry

CRS IBEX OCO-2

Mission Operations

timothy.perry@ngc.com

Office (703) 406-5976

Cell (301) 606-1430

 

cid:image001.png@01D542D6.6047A400