[Isocops] Command Approval Checklist Rev 8

Reno, Michelle mreno at swri.edu
Thu Jan 19 10:53:51 EST 2012


Hi All,
 
Attached is Rev 8 of the command approval checklist. It has been modified to verify no contacts or maneuvers occur during an eclipse, per Ryan. Comments/changes welcome.
 
Changes from Rev 7a:
was 7a:
Special Op

this orbit?

 

 

15Re desc

Date/Time

 

10Re desc

Date/Time

 

is 8:
15Re desc

Date/Time

 

 

10Re desc

Date/Time

 

10Re asc

Date/Time

 

 
was 7a:
Contact Commands

·         Each contact has 5 commands

1.     Verify STX on/off times, downlink rate against Orbit_oXXX.txt file

2.     Verify contacts in the previous ATS have not been duplicated 

3.     Verify all currently planned contacts in Orbit_xxx.txt are in the ATS.

4.     Verify each contact contains the following 5 commands

·         SetRelay stx,on 

·         SetDownlink2K  (2K, 40K, 64K, 160K, or 320K)

·         SetBilevelOutputControlReg STXMODE_Strobe,ON 

·         SetBilevelOutputControlReg COHERENT,ON 

·         SetRelay stx,off 

5.        Verify contact is not during an eclipse.

6.        If an APL contact is being used for an SSR Dump, the data rate should be at least 160 ksps & the SSR Dump New command should be included in the contact commands : 

·         SetRelay stx,on

·         SetDownlink160K

·         SetBilevelOutputControlReg STXMODE_Strobe,ON

·         SetBilevelOutputControlReg COHERENT,ON 

·         SSR_DUMP_NEW 

·         SetRelay stx,off 

is 8:
Contact Commands

·         Each contact has 5 commands

1.     Verify STX on/off times, downlink rate against Orbit_oXXX.txt file

2.     Verify contacts in the previous ATS have not been duplicated 

3.     Verify all currently planned contacts in Orbit_xxx.txt are in the ATS.

4.     Verify each contact contains the following 5 commands

·         SetRelay stx,on 

·         SetDownlink2K  (2K, 40K, 64K, 160K, or 320K)

·         SetBilevelOutputControlReg STXMODE_Strobe,ON 

·         SetBilevelOutputControlReg COHERENT,ON 

·         SetRelay stx,off 

5.        Verify contact is not during an eclipse.

6.        If an APL contact is being used for an SSR Dump, the data rate should be at least 160 ksps & the SSR Dump New command should be included in the contact commands : 

·         SetRelay stx,on

·         SetDownlink160K

·         SetBilevelOutputControlReg STXMODE_Strobe,ON

·         SetBilevelOutputControlReg COHERENT,ON 

·         SSR_DUMP_NEW 

·         SetRelay stx,off 

 
was 7a: N/A
is 8:
Eclipse Check

1.     Check OEF for eclipses during the orbit.

2.     Verify no contacts planned during an eclipse.

3.     Verify no maneuver planned during an eclipse.

This applies to all eclipses, not just moderate or long eclipses.

 

 

 
was 7a:
Inertial Maneuver Commands : Apogee

1.     Payload DESCENDING commands occur 1.5h before thruster enable.

·            DESCENDING_PL2 

2.     Spacecraft Housekeeping command occur 1h before thruster enable.

·         SetScState housekeeping 

3.     Verify Thruster enable command occurs within STF maneuver window.

4.     Verify cat bed heaters come on 55 min before burn

...

is 8:
Maneuver Commands : Apogee

1. Payload DESCENDING commands occur 1.5h before thruster enable.

· DESCENDING_PL2 

2. Spacecraft Housekeeping command occur 1h before thruster enable.

· SetScState housekeeping 

3. Verify Thruster enable command occurs within STF maneuver window.

4. Verify no eclipse occurs from cat bed heater on through set SC mode Mission.

5. Verify cat bed heaters come on 55 min before burn

...

 
was 7a:
Inertial Maneuver Commands : Perigee

1.     Verify cat bed heaters come on 55 min before burn

...

is 8:
Maneuver Commands : Perigee

1. Verify no eclipse occurs from cat bed heater on through set SC mode Mission.

2. Verify cat bed heaters come on 55 min before burn

...

~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Chelle Reno
Austin Mission Consulting
(210) 478-7337 (c)
~~~~~~~~~~~~~~~~~~~~~~~~~~~~

________________________________

From: isocops-bounces at lists.sr.unh.edu on behalf of Ibex Mission Operations
Sent: Thu 1/12/2012 5:04 PM
To: Bret Hautamaki; IBEX-FDG; IBEXOPS/ORB; ISOC at New Hampshire; John Cavallo; Tapley, Mark; Robert Lockwood; Roland Vanderspek; Ryan Tyler; Sheral Wesley; Thomas Regiec; Tim Perry; Walker Cross
Subject: [Isocops] IBEX Orbit# 154 v001 ATS (25 Jan - 4 Feb 12)


Guys,
    Here are the planning files and ATS for Orbit# 154.
Please respond to this thread for your approvals/comments.
All approvals/comments are required by 1900 UTC on 14 Jan 12.
Orbit# 152 Perigee activities start on 16 Jan 12 @ 1045 UTC

-- 
Sheral R. Wesley
SPVR., Satellite Operations
IBEX Mission OPS
(304) 279-6678

-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://lists.sr.unh.edu/mailman/private/isocops/attachments/20120119/79fa70dc/attachment-0001.html 
-------------- next part --------------
A non-text attachment was scrubbed...
Name: IBEX-Command-Approval-Checklist-Rev8.doc
Type: application/msword
Size: 97792 bytes
Desc: IBEX-Command-Approval-Checklist-Rev8.doc