[Trillian-users] Morse Hall power shutdown tomorrow

Mark Maciolek Mark.Maciolek at unh.edu
Tue May 19 11:23:21 EDT 2020


Hi,

Just a reminder that Morse Hall will be without power starting at 8am
tomorrow.

 RCC will start shutting down systems at 6am, including trillian, premise,
biomade and all systems in the data center.

Also, we will be shutting down Linux boxes throughout the building starting
at 6am with plans to turn them back on once power is restored and the data
center is back online.

Any questions should be directed to ops at sr.unh.edu

If we miss turning your system on, please email ops at sr.unh.edu and we will
get to it asap.

Mark
--Mark Maciolek
Network Administrator
Morse Hall Rm 338
Enterprise Technology & Services





More information about the Trillian-users mailing list