hi,

     Rescheduled for Monday morning at 7am.

Mark

On 1/10/2014 7:12 AM, Mark Maciolek wrote:
> hi,
>
>       This has been postponed to a future date.
>
> Mark
>
> On 1/7/2014 5:17 PM, Mark Maciolek wrote:
>> hi,
>>
>> Trillian will be offline Friday 1/10/2014 from 6:30am until early
>> afternoon.
>>
>> Work being done at the Philbrook chiller plant requires the Lenharth
>> Data Center be switched to the Morse Hall Rooftop Chiller on Friday
>> morning from 7am until noon. The current Morse Rooftop Chiller does not
>> have the capacity to handle the entire Lenharth Data Center.  To
>> reduce the load we will be shutting down Trillian at 6:30am on Friday
>> January 10 .  Trillian will come back online when the Data Center is
>> switched back to the Philbrook Chiller Plant.
>>
>> In April 2014 a 'new' 100 ton Morse Rooftop Chiller is scheduled to
>> be installed.  This new chiller will extended the Morse Rooftop
>> Chiller capacity to handle a full Lenharth Data Center load, including
>> the Cray.  Looking forward into the near future we expect events like
>> this to have no impact.
>>
>>
>> Mark
>>
>> _______________________________________________
>> Trillian-users mailing list
>> Trillian-users at lists.sr.unh.edu
>> http://lists.sr.unh.edu/mailman/listinfo/trillian-users
>>

-- 
-------------------------------------------------------------------------
Mark Maciolek		Network Administrator
mlm at sr.unh.edu	Morse Hall Room 338AB
University of New Hampshire    862-3050
-------------------------------------------------------------------------



More information about the Trillian-users mailing list