All, 

   Attached are the planning files for Orbit #664. Please respond to this thread with comments and approvals. Approvals for the Orbit 664 ATS are required by COB, 26 September 2024.

 

 

Please note the following: 

 

1.       No Battery Balancing

 

2.       Command Load Constraint Violation Report (CCVR) 

IBEX_2024_280_0664_v001.ccvr

# Input files:         1

#   IBEX_2024_280_o0664a_v001.scr

 

==========================

HARD CONSTRAINT VIOLATIONS

==========================

NO VIOLATIONS.

 

==========================

SOFT CONSTRAINT VIOLATIONS

==========================

IBX-CLC-016: No command to enable spin pulse protection was found after

             transition to science mode at 2024/10/07 09:34:56 UTC

IBX-CLC-016: No command to enable spin pulse protection was found after

             transition to science mode at 2024/10/11 15:01:58 UTC

 

==============

OTHER MESSAGES

==============

NO MESSAGES.