All, 

   Attached are the planning files for Orbit #655. Please respond to this thread with comments and approvals. Approvals for the Orbit 655 ATS are required by COB, 06 July 2024.

 

 

Please note the following: 

 

1.        NO Battery Balancing

 

2.        Command Load Constraint Violation Report (CCVR) 

IBEX_2024_198_o0655a_v001.ccvr

# Input files:         1

#   IBEX_2024_198_o0655a_v001.scr

 

==========================

HARD CONSTRAINT VIOLATIONS

==========================

NO VIOLATIONS.

 

==========================

SOFT CONSTRAINT VIOLATIONS

==========================

IBX-CLC-016: No command to enable spin pulse protection was found after

             transition to science mode at 2024/07/17 01:27:35 UTC

IBX-CLC-016: No command to enable spin pulse protection was found after

             transition to science mode at 2024/07/20 16:45:15 UTC

 

==============

OTHER MESSAGES

==============

NO MESSAGES.

 

 

Timothy E.Perry

CRS IBEX OCO-2

Mission Operations

timothy.perry@ngc.com

Office (703) 406-5976

IBEX MOC (703)404-7470

Cell (301) 606-1430