Attached are the planning files for Orbit #532. Please respond to this thread with comments and approvals.
Approvals are required by COB on 14 June 2021
Please note the following:
2.
Command Load Constraint Violation Report (CCVR)
IBEX_2021_175_o0532a_v001.ccvr
# Input files: 1
# IBEX_2021_175_o0532a_v001.scr
==========================
HARD CONSTRAINT VIOLATIONS
==========================
NO VIOLATIONS.
==========================
SOFT CONSTRAINT VIOLATIONS
==========================
IBX-CLC-016: No command to enable spin pulse protection was found after
transition to science mode at 2021/06/25 07:06:45 UTC
IBX-CLC-016: No command to enable spin pulse protection was found after
transition to science mode at 2021/06/29 04:31:39 UTC
==============
OTHER MESSAGES
==============
NO MESSAGES.