All,
Attached are the planning files for Orbit #524. Please respond to this thread with comments and approvals.
Approvals are required by COB on 02 April 2021
Please note the following:
Begin 2021/04:21:11:00:00– End 2021/04:21:12:30:00
5.
# Orbit# 522 Reset Master Timer - 2021/04:03:03:15:00
6.
Command Load Constraint Violation Report (CCVR)
# Input files: 1
# IBEX_2021_103_o0524a_V001.scr
==========================
HARD CONSTRAINT VIOLATIONS
==========================
NO VIOLATIONS.
==========================
SOFT CONSTRAINT VIOLATIONS
==========================
IBX-CLC-016: No command to enable spin pulse protection was found after
transition to science mode at 2021/04/12 10:16:35 UTC
IBX-CLC-016: No command to enable spin pulse protection was found after
transition to science mode at 2021/04/16 11:11:24 UTC
==============
OTHER MESSAGES
==============
NO MESSAGES.
Timothy E.Perry
CRS IBEX OCO-2
Mission Operations
timothy.perry@ngc.com