All,
We have the first recovery schedule contact scheduled for 18:00 - 19:30 UTC. That’s 10:00 am PST, 11:00 am MST, 12:00 pm CST, 1:00 pm EST.
We’ll hold an FRB using the IBEX party line just before that at 09:30 am PST, 10:30 am MST, 11:30 am CST, 12:30 pm EST. Sorry for the short notice.
IBEX party line details:
888-330-1716
Conference code: 4895952
Here’s what I plan to walk through.
Thanks,
Nigel
-------------------------
Spacecraft status:
Contingency State
ACS in High mode ?
The star tracker is off
CEU, Lo and Hi are off
Perigee maneuver did not execute
Recovery activities already performed:FC Back orbit buffer re-enabled and dumped
Reference power tracking mode reset to Voltage.
Planning progress:
Two 90 minute SSC contacts scheduled so far
Recovery contacts ATS to be prepared (approval required: MOM, ISOC) or blind acquisition
New orbit 507 BUS and INST ATS files in preparation (v002): approval required: MOM, ISOC
STF files for replacement perigee maneuver. Execution time between the first and second recovery contact. Maneuver ATS to be prepared: approval required: MOM, ISOC
Spacecraft Recovery CAR is in preparation. It will be circulated and approved before the first recovery contact. Approval required: MOM, SYS, MOC, ISOC
Instrument Recovery CAR is in preparation. It will be circulated and approved before the second recovery contact. Approval required: MOM, MOC, ISOC, CEU, Hi, Lo
Recovery Contacts:
IBEX,USHI01,ADD,11/09/20,314,18:00:00,11/09/20,314,19:30:00,LAHO 0K IBEX-2 Orbit# 506 BCR Recovery #1 Contact 13 Asc
Spacecraft recovery, uplink recovery contacts ATS, replacement maneuver ATS
Personnel: MOC, MOM, ISOC (SYS on call)
10:00 am PST, 11:00 am MST, 12:00 pm CST, 1:00 pm EST
IBEX,AUWA01,ADD,11/09/20,314,22:00:00,11/09/20,314,23:30:00,LAHO 160K IBEX-2 Orbit# 506 BCR Recovery #2 Contact 13.5 Asc
Confirm nominal maneuver execution
Start payload recovery
Personnel: MOC, MOM, ISOC, Lo, Hi, (CEU on call)
2:00 pm PST, 3:00 pm MST, 4:00 pm CST, 5:00 am EST
IBEX,USHI02,ADD,11/10/20,315,19:00:00,11/10/20,315,20:45:00,LAHO 2K IBEX-2 Orbit# 506 BCR Recovery #3 Contact
Finish payload recovery, load orbit 493 v002 BUS and INST ATSs. Load orbit 494 & 495 ATS.
Personnel: MOC, MOM, ISOC, (Lo, Hi & CEU on call)
11:00 am PST, 12:00 pm MST, 1:00 pm CST, 2:00 pm EST