[Ibex-maneuver-engineering] Maneuver Closeout Actions
Reno, Michelle
mreno at swri.edu
Tue Jul 5 08:49:45 EDT 2011
Hi Team,
Below is a list of closeout action items & who is responsible for them.
Most of them can be completed by the end of the week. If you feel your
action will take more time please email Robert & I with the reason and
an ETA.
There is one small SYS/ACS action that is not on the list.
Implementation is still being discussed. I will send this action in a
separate email.
Chelle
Maneuver Closeout
* SYS : Final Fuel Usage Table
* Bret : Step 47 telemetry change
* ACS : repointing time per degree as a function of current
fill level. Assess whether this will need to be changed again before
EOL. Use to change rote timing now & schedule next rote change.
* SYS : tank pressure yellow limits as a function of time
(change every year, July 1). Set limits for what is expected 1 year, 3
months from set date, to identify any slow leaks early.
* Sheral/Tim : List of contact time, station, alt, Eb/N0,
station power, notes about pass
* Sheral/Tim : Lessons learned about USN troubleshooting
* Mark/Ken : Compensating for the deadband
* Steve : Thruster models
* FDG : Final Orbit Analysis package
* ISOC : Update to Geoff's ISOC SW document to include new
software
* Me : Final closeout package - MAC checklists, final timeline,
etc
Extended Mission Outstanding Items
* SYS/EPS : Battery cell balancing plan for extended mission
* SYS/EPS : Moderate eclipse diagnostic procedure
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://lists.sr.unh.edu/pipermail/ibex-maneuver-engineering/attachments/20110705/04d97499/attachment.html
More information about the Ibex-maneuver-engineering
mailing list