plans to take the BioMade HPC Core offline early on Wednesday 2/2/22
and bring it back online by late afternoon Thursday 2/3/22. Please
plan your jobs so they complete before 6am on 2/2. Any running jobs
will be terminated on the morning of 2/2.
Normal BIOS and OS updates will be
done for the BioMade HPC Core hardware. Additionally the clusters CPU
Only Nodes will each receive an A100 GPU, purchased by the BioMade
grant in 2021Q4. This hardware addition will make all of the BioMade
HPC Core compute nodes GPU nodes.
The GPU card installs and upgrades will take all day
Wednesday. But we may be able to bring the BioMade HPC Core back
online before the end of day Thursday.
Email will be sent when we the BioMade HPC Core is back in
service, and two more email reminders are planned.
Expect reminder email on:
Wednesday 1/26 & Monday 1/31
Back online
email sometime on: 2/3
Robert E.
Anderson
Associate Director
Univ of NH Research Computing
Center